Stormwater System Restoration

The Grande on Sand Key Condominium, Inc. | 1180 Gulf Blvd, Clearwater Beach, FL 33767 | NV5 Project #2025.124.312
Contract
75 Days
From NTP
Work Hours
9-5 PM
Weekdays
Work Areas
4
2 Ponds + 2 Laterals
Pipe Cleaning
2 Pipes
30"x19" RCP
Sod
St. Augustine
All Ponds & Laterals
Maintenance Access
5' Wide
4" Shell Base
Overall Project Progress0%

Owner

The Grande on Sand Key Owner's Association, Inc.
  • 1180 Gulf Blvd
  • Clearwater Beach, FL 33767

Engineer

NV5 — Jose R. Cuarta, P.E.
  • 12467 Telecom Drive
  • Tampa, FL 33637
  • Jose.Cuarta@NV5.com | Adam.Bondi@NV5.com

Contractor

Firm Foundations Asphalt & Concrete LLC
  • Arthur Wilmoth, Senior Project Manager
  • 10701 N Nebraska Ave, Tampa, FL 33612
  • 813-853-6597 | CBC1267421

Key Dates & Requirements

Contract Terms
  • Start within 10 calendar days of NTP
  • Complete within 75 calendar days of NTP
  • Bond: P&P at 10%/110% + 2-yr Maintenance
  • Pinellas County & City of Clearwater standards
  • FDOT Erosion & Sediment Control Manual

Subcontractors

Pipe Restoration Systems

Pipe & Structure Cleaning + Camera Inspection
  • 128 Sarasota Center Blvd, Sarasota, FL 34240

JNL Land Management

Clearing, Grubbing & Grading
  • 401 E Chapman Rd, Lutz, FL 33549

Paradise Yards & Design LLC

Sod, Watering, Shell & Arborist Services
  • 601 Westbrook Ave, Brandon, FL 34240

GPRS Inc

Underground Private Locates
  • 1901 Indian Wood Circle, Maumee, OH 43537

A-1 Silt & Erosion

Silt Fence & Inlet Protection
  • Zephyrhills, FL

Land Precision Corporation

Grade Stakes, Top of Bank Stakes & As-Builts
  • 2683 Sunset Point Rd, Clearwater, FL 33759

Scope of Work — Area Breakdown

North Pond MAJOR

Sheet 3 | North Stormwater Pond
  • Install Type III silt fence along pond perimeter per FDOT standards
  • Install inlet protection at all stormwater inlets
  • Construct 5' wide shell maintenance access (4" shell base, grade existing alignment)
  • Modify approximately 4 sections of aluminum fence — cut lower pickets for unobstructed flow
  • Clear vegetation within proposed grading areas (palms removed & replanted by owner)
  • Regrade pond banks to proposed elevations per plan
  • Relocate all existing bubblers and M.E.S. to match proposed grades
  • Sod pond with St. Augustine sod including bottom
  • Install stabilized access point for construction equipment
Key Notes: Aluminum fence modification at outfall | 5' shell maintenance access | Additional Type III silt fence per Addendum #1

South Pond MOST COMPLEX

Sheet 4 | South Stormwater Pond
  • Replace damaged control structure concrete top at south pond
  • Replace steel grate frame (reuse existing steel grate)
  • Protect oak tree at northwest corner with barricades
  • Professional arborist to trim oak tree & perform root trimming near excavation
  • Owner to remove and replant 3 palms located east of curb inlet
  • Clear all other vegetation within proposed grading areas
  • Regrade pond banks to proposed elevations per plan
  • Relocate all existing bubblers and M.E.S. to match proposed grades
  • Sod pond laterals and banks with St. Augustine (bottom of south pond excluded per Addendum #1)
Key Notes: Control structure replacement is critical path | Oak tree requires professional arborist | Owner handles palm relocation

Laterals & Drainage MODERATE

North & South Laterals | Driveway Connections
  • Clean two (2) 30"x19" pipes connecting ponds (camera inspection by Pipe Restoration Systems)
  • Grade laterals to proposed drainage elevations
  • Sod both laterals with St. Augustine sod
  • Adjust/relocate bubblers and M.E.S. to match proposed grades
  • Stake limits of proposed regrading areas per plan
Alternate Bid: Cleaning the drainage sewer system in driveways connecting ponds with laterals (requested by owner)

Site Work & Erosion Control THROUGHOUT

All Areas | Project-Wide
  • Install Type III silt fence around all work zones per FDOT Erosion & Sediment Control Manual
  • Install inlet protection at all stormwater inlets
  • Establish stabilized access and stockpile protection
  • Daily site cleaning Monday-Friday (blow and clean)
  • Equipment staging nightly in designated area
  • Port-o-let placement secured away from drainage paths
  • Underground private locates at all digging sites (GPRS)
  • Grade stakes, top of bank stakes, and as-builts (Land Precision)
  • PPE required: Hardhats, steel toe shoes, reflective vests, matching company shirts
  • Pavers removed during work to be kept by owner
Standards: Pinellas County BMP Requirements | City of Clearwater Coastal Protection | FDOT Erosion & Sediment Control Manual

Clean Well Drained Soils Specification

NV5 Memorandum — March 19, 2026
  • USCS Classification: SW
  • 3/8" Sieve: 100% passing
  • No. 4: 95-100% | No. 10: 80-100% | No. 40: 10-60%
  • No. 200: 0-5% (≤3% preferred)
  • Hydraulic Conductivity (K): ≥1 x 10³ cm/sec
  • Uniformity Coefficient: CU > 4
  • Clean sand (SP or SW), less than 5% passing No. 200, non-plastic, free of organics
Note: Provide clean sand suitable for drainage with high permeability. Uniform sand preferred.

Project Schedule — 75 Calendar Day Window

Contract
75 Days
Work Days
~54
Weather Buffer
~10 Days
Critical Path
South Pond
Task Wk 1Wk 2Wk 3Wk 4Wk 5 Wk 6Wk 7Wk 8Wk 9Wk 1011
MTWTFMTWTF MTWTFMTWTF MTWTFMTWTF MTWTFMTWTF MTWTFMTWTFM
PRE-CONSTRUCTION
Mobilization / Site Setup
Private Locates (GPRS)
Silt Fence + Inlet Protection
Grade Stakes + Layout (Land Precision)
NORTH POND — Regrading + Fence Mod + Maintenance Access
Clearing & Vegetation Removal
Pond Regrading + Bubbler Relocation
Aluminum Fence Modification
5' Shell Maintenance Access
SOUTH POND — Control Structure + Oak Tree + Regrading (CRITICAL PATH)
Oak Tree Barricade + Arborist
Clearing & Vegetation Removal
Control Structure + Grate Frame
Pond Regrading + Bubbler Relocation
LATERALS & PIPE CLEANING
Pipe Cleaning + Camera Inspection
Lateral Grading + MES Relocation
SODDING & CLOSEOUT
Sod All Areas (St. Augustine)
Sweep / Cleanup / Silt Removal
Final As-Builts + Inspection
Punch List / Corrections
Mobilization
Erosion Control
Clearing/Demo
Drainage/Pipe
Grading
Concrete/Structural
Sodding
Cleanup
Inspection
Punch List

Project Progress

Overall Completion0%
North Pond
0%
South Pond
0%
Laterals
0%
Site Work
0%
🚧

No updates yet

Progress updates will appear here once the project begins. Check back soon!

Field Notes

Field notes are added during construction via the Admin panel.

📝

No field notes yet

Field notes will be added here during construction — observations, issues, RFIs, and daily logs.

Project Documents

Key project documents available for reference.