Stormwater System Restoration
The Grande on Sand Key Condominium, Inc. | 1180 Gulf Blvd, Clearwater Beach, FL 33767 | NV5 Project #2025.124.312
Contract
75 Days
From NTP
Work Hours
9-5 PM
Weekdays
Work Areas
4
2 Ponds + 2 Laterals
Pipe Cleaning
2 Pipes
30"x19" RCP
Sod
St. Augustine
All Ponds & Laterals
Maintenance Access
5' Wide
4" Shell Base
Overall Project Progress0%
Owner
The Grande on Sand Key Owner's Association, Inc.
- 1180 Gulf Blvd
- Clearwater Beach, FL 33767
Engineer
NV5 — Jose R. Cuarta, P.E.
- 12467 Telecom Drive
- Tampa, FL 33637
- Jose.Cuarta@NV5.com | Adam.Bondi@NV5.com
Contractor
Firm Foundations Asphalt & Concrete LLC
- Arthur Wilmoth, Senior Project Manager
- 10701 N Nebraska Ave, Tampa, FL 33612
- 813-853-6597 | CBC1267421
Key Dates & Requirements
Contract Terms
- Start within 10 calendar days of NTP
- Complete within 75 calendar days of NTP
- Bond: P&P at 10%/110% + 2-yr Maintenance
- Pinellas County & City of Clearwater standards
- FDOT Erosion & Sediment Control Manual
Subcontractors
Pipe Restoration Systems
Pipe & Structure Cleaning + Camera Inspection
- 128 Sarasota Center Blvd, Sarasota, FL 34240
JNL Land Management
Clearing, Grubbing & Grading
- 401 E Chapman Rd, Lutz, FL 33549
Paradise Yards & Design LLC
Sod, Watering, Shell & Arborist Services
- 601 Westbrook Ave, Brandon, FL 34240
GPRS Inc
Underground Private Locates
- 1901 Indian Wood Circle, Maumee, OH 43537
A-1 Silt & Erosion
Silt Fence & Inlet Protection
- Zephyrhills, FL
Land Precision Corporation
Grade Stakes, Top of Bank Stakes & As-Builts
- 2683 Sunset Point Rd, Clearwater, FL 33759
Scope of Work — Area Breakdown
North Pond MAJOR
Sheet 3 | North Stormwater Pond
- Install Type III silt fence along pond perimeter per FDOT standards
- Install inlet protection at all stormwater inlets
- Construct 5' wide shell maintenance access (4" shell base, grade existing alignment)
- Modify approximately 4 sections of aluminum fence — cut lower pickets for unobstructed flow
- Clear vegetation within proposed grading areas (palms removed & replanted by owner)
- Regrade pond banks to proposed elevations per plan
- Relocate all existing bubblers and M.E.S. to match proposed grades
- Sod pond with St. Augustine sod including bottom
- Install stabilized access point for construction equipment
Key Notes: Aluminum fence modification at outfall | 5' shell maintenance access | Additional Type III silt fence per Addendum #1
South Pond MOST COMPLEX
Sheet 4 | South Stormwater Pond
- Replace damaged control structure concrete top at south pond
- Replace steel grate frame (reuse existing steel grate)
- Protect oak tree at northwest corner with barricades
- Professional arborist to trim oak tree & perform root trimming near excavation
- Owner to remove and replant 3 palms located east of curb inlet
- Clear all other vegetation within proposed grading areas
- Regrade pond banks to proposed elevations per plan
- Relocate all existing bubblers and M.E.S. to match proposed grades
- Sod pond laterals and banks with St. Augustine (bottom of south pond excluded per Addendum #1)
Key Notes: Control structure replacement is critical path | Oak tree requires professional arborist | Owner handles palm relocation
Laterals & Drainage MODERATE
North & South Laterals | Driveway Connections
- Clean two (2) 30"x19" pipes connecting ponds (camera inspection by Pipe Restoration Systems)
- Grade laterals to proposed drainage elevations
- Sod both laterals with St. Augustine sod
- Adjust/relocate bubblers and M.E.S. to match proposed grades
- Stake limits of proposed regrading areas per plan
Alternate Bid: Cleaning the drainage sewer system in driveways connecting ponds with laterals (requested by owner)
Site Work & Erosion Control THROUGHOUT
All Areas | Project-Wide
- Install Type III silt fence around all work zones per FDOT Erosion & Sediment Control Manual
- Install inlet protection at all stormwater inlets
- Establish stabilized access and stockpile protection
- Daily site cleaning Monday-Friday (blow and clean)
- Equipment staging nightly in designated area
- Port-o-let placement secured away from drainage paths
- Underground private locates at all digging sites (GPRS)
- Grade stakes, top of bank stakes, and as-builts (Land Precision)
- PPE required: Hardhats, steel toe shoes, reflective vests, matching company shirts
- Pavers removed during work to be kept by owner
Standards: Pinellas County BMP Requirements | City of Clearwater Coastal Protection | FDOT Erosion & Sediment Control Manual
Clean Well Drained Soils Specification
NV5 Memorandum — March 19, 2026
- USCS Classification: SW
- 3/8" Sieve: 100% passing
- No. 4: 95-100% | No. 10: 80-100% | No. 40: 10-60%
- No. 200: 0-5% (≤3% preferred)
- Hydraulic Conductivity (K): ≥1 x 10³ cm/sec
- Uniformity Coefficient: CU > 4
- Clean sand (SP or SW), less than 5% passing No. 200, non-plastic, free of organics
Note: Provide clean sand suitable for drainage with high permeability. Uniform sand preferred.
Project Schedule — 75 Calendar Day Window
Contract
75 Days
Work Days
~54
Weather Buffer
~10 Days
Critical Path
South Pond
| Task | Wk 1 | Wk 2 | Wk 3 | Wk 4 | Wk 5 | Wk 6 | Wk 7 | Wk 8 | Wk 9 | Wk 10 | 11 | ||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| M | T | W | T | F | M | T | W | T | F | M | T | W | T | F | M | T | W | T | F | M | T | W | T | F | M | T | W | T | F | M | T | W | T | F | M | T | W | T | F | M | T | W | T | F | M | T | W | T | F | M | |
| PRE-CONSTRUCTION | |||||||||||||||||||||||||||||||||||||||||||||||||||
| Mobilization / Site Setup | |||||||||||||||||||||||||||||||||||||||||||||||||||
| Private Locates (GPRS) | |||||||||||||||||||||||||||||||||||||||||||||||||||
| Silt Fence + Inlet Protection | |||||||||||||||||||||||||||||||||||||||||||||||||||
| Grade Stakes + Layout (Land Precision) | |||||||||||||||||||||||||||||||||||||||||||||||||||
| NORTH POND — Regrading + Fence Mod + Maintenance Access | |||||||||||||||||||||||||||||||||||||||||||||||||||
| Clearing & Vegetation Removal | |||||||||||||||||||||||||||||||||||||||||||||||||||
| Pond Regrading + Bubbler Relocation | |||||||||||||||||||||||||||||||||||||||||||||||||||
| Aluminum Fence Modification | |||||||||||||||||||||||||||||||||||||||||||||||||||
| 5' Shell Maintenance Access | |||||||||||||||||||||||||||||||||||||||||||||||||||
| SOUTH POND — Control Structure + Oak Tree + Regrading (CRITICAL PATH) | |||||||||||||||||||||||||||||||||||||||||||||||||||
| Oak Tree Barricade + Arborist | |||||||||||||||||||||||||||||||||||||||||||||||||||
| Clearing & Vegetation Removal | |||||||||||||||||||||||||||||||||||||||||||||||||||
| Control Structure + Grate Frame | |||||||||||||||||||||||||||||||||||||||||||||||||||
| Pond Regrading + Bubbler Relocation | |||||||||||||||||||||||||||||||||||||||||||||||||||
| LATERALS & PIPE CLEANING | |||||||||||||||||||||||||||||||||||||||||||||||||||
| Pipe Cleaning + Camera Inspection | |||||||||||||||||||||||||||||||||||||||||||||||||||
| Lateral Grading + MES Relocation | |||||||||||||||||||||||||||||||||||||||||||||||||||
| SODDING & CLOSEOUT | |||||||||||||||||||||||||||||||||||||||||||||||||||
| Sod All Areas (St. Augustine) | |||||||||||||||||||||||||||||||||||||||||||||||||||
| Sweep / Cleanup / Silt Removal | |||||||||||||||||||||||||||||||||||||||||||||||||||
| Final As-Builts + Inspection | |||||||||||||||||||||||||||||||||||||||||||||||||||
| Punch List / Corrections | |||||||||||||||||||||||||||||||||||||||||||||||||||
Project Progress
Overall Completion0%
North Pond
0%
South Pond
0%
Laterals
0%
Site Work
0%
🚧
No updates yet
Progress updates will appear here once the project begins. Check back soon!
Field Notes
Field notes are added during construction via the Admin panel.
📝
No field notes yet
Field notes will be added here during construction — observations, issues, RFIs, and daily logs.
Project Documents
Key project documents available for reference.
📄 Request for Bids
Section 00010 — Sealed Proposal Requirements
📄 Instructions to Bidder
Section 00100 — Bidding Requirements & Qualifications
📄 Bid Packet
Complete Bid Submission — Firm Foundations
📄 Addendum #1
Pre-Bid Meeting Q&A, Engineer Revisions, Drawing Changes
📄 Erosion Control Plan
FDOT Standards, BMP Requirements, Environmental Protections
📄 MOT & Safety Plan
Traffic Control, Safety Protocols, Work Hours
📄 Certificate of Insurance
Insurance Coverage Documentation
📄 Statement of Similar Work
Firm Foundations Project Experience & Qualifications
📄 Clean Well Drained Soils Spec
NV5 Memorandum — USCS SW Classification, Sieve Analysis